Bay Area
Backup units can't be the bridge; new prime gas engines need offsets once the whole site passes 10 tons of NOx a year (about 5 MW of gas on an otherwise clean site).
Only with a months-long air permit. Together with California.
Permitted plant: Possible (With offsets past 10 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Generators permitted as emergency backup at Bay Area data centers can only run for real, unforeseeable outages plus 50 hours a year of testing, so they cannot carry a site while it waits for power; a new engine meant to run as prime power needs a separate, stricter permit with offsets once the site passes 10 tons of NOx a year.
Permitted gas generation
Backup generators can't run as bridge power. A new prime gas engine can be permitted with best available controls, plus a health risk assessment if its toxic emissions pass district trigger levels. Once the whole site's potential NOx passes 10 tons a year (about 5 MW of gas on an otherwise clean site), the increase must be offset. Up to 35 tons the district supplies offsets from its small-facility bank if the bank has credits and the operator has none; at 35 tons or more the operator buys its own at 1.15 to 1.
Rentals kept under 12 months
California's portable equipment registration (PERP) covers gas engines but isn't valid for supplying a site's primary power. The only exceptions are utility outages, maintenance, a failed backup generator (up to 180 days), and electrical-upgrade work (90 days, or longer if the district agrees in writing). Source
Details
- Who it covers
- new and existing
- Where
- Only southwestern Solano and southern Sonoma are in the Bay Area air district
- Status
- In force
- Effective
- July 25, 2007
- Authority
- Bay Area Air Quality Management District (BAAQMD)
- Last checked
- November 8, 2026
Sources
- BAAQMD Data Centers page (last updated Oct 16, 2026) primary
Permits do not allow the engines to be used to support the electric grid.
- BAAQMD Regulation 9, Rule 8, Section 9-8-237 (adopted July 25, 2007) primary
The enforcement of a contractual obligation the owner or operator has with a third party or any other party is foreseeable.
- BAAQMD Regulation 2, Rule 2 (New Source Review), Section 2-2-302 (amended Dec 6, 2017) primary
facility that will have the potential to emit more than 10 tons per year of NOx or POC ... offsets must be provided
- BAAQMD Compliance Advisory: Stationary Emergency Standby Engine Usage, Reg 9-8 (Aug 23, 2021) primary
An engine operating pursuant to the ELRP is doing so as a result of a contractual obligation rather than as a result of power supply failure.
- BAAQMD Air Quality FAQ (jurisdiction) primary
Alameda, Contra Costa, Marin, Napa, San Francisco, San Mateo, Santa Clara, southwestern Solano, and southern Sonoma
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.