San Joaquin Valley
No ban. An engine run because the grid hasn't failed is not an emergency engine; a prime gas engine must meet 11 ppm NOx, and the site owes offsets once its NOx potential reaches 20,000 lb a year (about 5 MW of gas 24/7, our estimate).
Only with a months-long air permit. Together with California.
Permitted plant: Possible (Offsets from 10 tons NOx/yr site-wide)Rentals under 12 months, no air permit: No
Rule 4702 says an engine is not an emergency standby engine if it is used to reduce demand for electrical power when line service has not failed, so a bridge engine is a regular stationary engine subject to Table 2 (11 ppmv NOx for generic rich- and lean-burn spark-ignited engines). Rule 2201 requires offsets when the post-project stationary source potential to emit equals or exceeds 20,000 lb/yr of NOx (Table 4-1).
Permitted gas generation
A bridge engine is a regular stationary engine: district permit, BACT, 11 ppm NOx, and offsets once the site's NOx potential reaches 20,000 lb a year (about 5 MW of gas running 24/7 on an otherwise clean site, our estimate).
Rentals kept under 12 months
California's portable registration can't supply a site's primary power, so rented units need a district permit like any prime engine. Source
Details
- Who it covers
- new and existing
- Where
- Only the San Joaquin Valley portion of Kern County is in SJVAPCD (boundary from background knowledge; not checked against the boundary regulation in this pass)
- Status
- In force
- Effective
- August 9, 2023
- Authority
- San Joaquin Valley Unified Air Pollution Control District (SJVAPCD)
- Last checked
- November 8, 2026
Sources
- SJVAPCD Rule 2201 (amended Apr 20, 2023; in effect Aug 9, 2023), §4.5.3 Table 4-1 primary
offsets shall be required if the post-project Stationary Source Potential to Emit (SSPE2) equals or exceeds the following offset threshold levels: ... NOx 20,000
- SJVAPCD Rule 4702 (amended Aug 19, 2021), §3.15 and Table 2 primary
An engine shall not be considered to be an emergency standby engine if it is used: (1) to reduce the demand for electrical power when normal electrical power line service has not failed
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.