Rentals can't supply primary power; a permitted gas plant needs a district permit and, past a site-wide line, offsets.
Only with a months-long air permit.
Permitted plant: Possible (District permit, with offsets)Rentals under 12 months, no air permit: No
California's statewide portable equipment registration (PERP) isn't valid for supplying a site's primary power, except utility outages, maintenance, a failed backup generator (up to 180 days) and electrical-upgrade work (90 days, or longer if the district agrees in writing). So rented units need a district permit like any prime engine. Each air district permits prime gas engines with strict NOx limits and requires offsets once the whole site passes its line, from about 2 MW of gas in the South Coast to about 12 MW in San Diego, Imperial and the High Desert (our estimates).
Permitted gas generation
No statewide ban. A new prime gas engine needs an air district permit with best available controls, and offsets once the site passes the district's line (about 2–12 MW of gas, our estimates).
Rentals kept under 12 months
PERP registration isn't valid for supplying a site's primary power. The only exceptions are utility outages, maintenance, a failed backup generator (up to 180 days), and electrical-upgrade work (90 days, or longer if the district agrees in writing). Source
Details
- Who it covers
- new and existing
- Where
- Statewide
- Status
- In force
- Authority
- California Air Resources Board (PERP); local air districts
- Last checked
- November 8, 2026