Hernando County, FL

Pauses county or city approvals to build or expand data centers, generators included.

Likely no gas route.

Permitted plant: No (Moratorium to Jun 23, 2027)Rentals under 12 months, no air permit: Likely no

Hernando County paused, for 365 days from its effective date, the issuance of development orders or permits, including building permits, "that allows for the initiation, construction, expansion, or modification of existing or new data centers" in unincorporated areas. Data center has the state-law meaning, which includes large-scale data centers. Existing lawfully built development is not affected, and applications received before the effective date continue to be processed. The pause can be extended once by up to 120 days.

Permitted gas generation

Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).

Rentals kept under 12 months

Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source

What's next

Details

Who it covers
new and existing data centers in unincorporated Hernando County; expansions and modifications paused; lawfully built existing development and pre-filed applications unaffected
Where
Unincorporated Hernando County only
Status
In force
Effective
June 23, 2026
Ends
June 23, 2027
Authority
Hernando County Board of County Commissioners, FL (June 23, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.