Leon County, FL (50 MW+)

Pauses county approvals to build, expand or operate sites of 50 MW or more, generators included.

Likely no gas route.

Permitted plant: No (Moratorium to Apr 13, 2028)Rentals under 12 months, no air permit: Likely no

Leon County paused for 18 months the acceptance, review or approval of rezonings, conditional uses, development permits, site plans, building permits and other approvals "for the construction, expansion, or operation of facilities serving large load customers, including large-scale data centers" in unincorporated areas. Large load means an anticipated monthly peak of 50 MW or more at one location. Properties with documented damage from Hurricanes Debby or Helene are exempt.

Permitted gas generation

Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).

Rentals kept under 12 months

Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source

What's next

Details

Who it covers
facilities serving large load customers (50 MW+), new and existing, in unincorporated Leon County
Size
50 MW or more
Where
Unincorporated Leon County only
Status
In force
Effective
October 13, 2026
Ends
April 13, 2028
Authority
Leon County Board of County Commissioners, FL (Oct 13, 2026)
Last checked
November 8, 2026

Sources