Levy County, FL

Pauses county or city approvals to build or expand data centers, generators included.

Likely no gas route.

Permitted plant: No (Moratorium to Oct 6, 2027)Rentals under 12 months, no air permit: Likely no

Levy County paused, for 12 months from its effective date, the acceptance, review and approval of development permits and development orders for data center facilities in unincorporated areas. The definition says such facilities may include power generators. Existing permits and orders stay valid.

Permitted gas generation

Local approvals to establish or expand a covered data center are paused. A generator addition needing a local permit is paused (our reading). It pauses new data centers too, and likely battery additions at existing ones (our reading).

Rentals kept under 12 months

Rented units need no Florida air permit, but a local building, electrical or site approval for them at a covered data center would be paused (our reading). Source

What's next

Details

Who it covers
new data center approvals and new permits at existing data center facilities in unincorporated Levy County (any size); existing permits unaffected
Where
Unincorporated Levy County only
Status
In force
Effective
October 6, 2026
Ends
October 6, 2027
Authority
Levy County Board of County Commissioners, FL (Oct 6, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.