Forsyth County, GA
Zoning limits generators at data centers to emergency backup and testing; 'emergency' is not defined.
Likely no gas route.
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Forsyth County, GA's data center zoning standard says: "With the exception of testing activities, generator use is limited to emergency backup use only." (UDC Sec. 16-4.10(E)). The ordinance does not define 'emergency' or 'backup' and does not separately bar other on-site generation. We read it as barring a generator fleet that runs 24/7 or as bridge power while a site waits for a grid connection, because that is neither emergency nor backup use (our reading). It does not meet the skill's block test on its own text. Adopted March 6, 2025 (Municode ordinance record). Testing is limited to 9 a.m. to 5 p.m. The text says nothing about existing sites.
Permitted gas generation
Generator use other than testing is limited to emergency or backup use. Whether a wait for grid service counts as an emergency is not stated (our reading: it does not).
Rentals kept under 12 months
The limit applies to all generator use on the site and does not distinguish owned from rented units. We read it as covering rented units (our reading; the text does not name them). Source
Details
- Who it covers
- all data centers (conditional use in industrial districts)
- Where
- Unincorporated Forsyth County only
- Status
- In force
- Effective
- March 6, 2025
- Authority
- Forsyth County, GA (Board of Commissioners, March 6, 2025)
- Last checked
- November 8, 2026
Sources
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.