Griffin, GA

Zoning bars primary on-site power generation at data centers; prime power is not a valid backup use.

No gas route.

Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No

Griffin's data center rules (Ord. 26-007, adopted May 26, 2026) say: "No primary onsite power generation shall be permitted." Generators may be used only for testing and "temporary or emergency backup use", and "Use as prime power, rate curtailment, and storm avoidance shall not constitute a valid temporary or emergency backup use." Data centers are allowed only by special use permit in the Planned Industrial Development district, as Minor (up to 10,000 sq ft, no substation) or Major (10,000 to 275,000 sq ft) facilities. The applicant must show a letter from the power provider confirming capacity before a land disturbance permit. The ordinance does not say how it treats existing data centers.

Permitted gas generation

No primary on-site power generation. Prime power is expressly not a valid backup use, so a bridge running in place of grid power is barred (our reading of 'prime power').

Rentals kept under 12 months

The ban reaches 'generator use' of any kind beyond testing and temporary or emergency backup, and excludes prime power. We read that as covering rented units run as prime power (our reading; the text does not name rentals). Source

Details

Who it covers
Minor and Major data centers approved by special use permit in the PID district (single building up to 275,000 sq ft); existing sites not addressed
Where
City of Griffin only (Spalding County zones separately)
Status
In force
Effective
May 26, 2026
Authority
City of Griffin, GA (Board of Commissioners, May 26, 2026)
Last checked
November 8, 2026

Sources