Monroe County, GA
Zoning requires utility power for all data center operations and bans gas or diesel generators as primary power.
No gas route.
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
Monroe County's data center standards, adopted 5-0 on April 7, 2026, say: "All operational power shall be provided by a regulated public utility." They also say: "The use of permanent or semi-permanent diesel or gas-powered generators as the primary source of power is strictly prohibited. Backup generators are permitted only for emergency and system testing purposes." Data centers are allowed only as a special use in the M-1 district, on at least 900 acres, with transmission-level (115 kV or more) service unless the County Utility Director grants an exemption. Generators must be Tier 4 final, enclosed, and tested only 10 a.m. to 4 p.m. on weekdays. The same meeting lifted the county's data center moratorium. The ordinance does not say how it treats data centers approved before it.
Permitted gas generation
All operational power must come from a regulated public utility, and gas or diesel generators can't be the primary power source. Generators are allowed only for emergencies and testing.
Rentals kept under 12 months
The ban names 'permanent or semi-permanent' generators, and separately requires that all operational power come from a regulated utility. We read that as covering rented units kept for months (our reading; the text does not name rentals). Source
Details
- Who it covers
- data centers approved as special uses in M-1 under the amended UDO Sec. 4.02.23 (900-acre minimum lot); treatment of the county's two previously approved data centers is not stated
- Where
- Unincorporated Monroe County only (the cities of Forsyth and Culloden zone separately)
- Status
- In force
- Effective
- April 7, 2026
- Authority
- Monroe County, GA (Board of Commissioners, April 7, 2026)
- Last checked
- November 8, 2026
Sources
- Monroe County data center ordinance amendment (agenda text, April 2026) primary
- Monroe County Board of Commissioners minutes, April 7, 2026 primary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.