Pittsfield Charter Township, MI
Zoning bars on-site engines and generators for continuous, prime, peaking or routine non-emergency power at data centers, from Nov 9, 2026.
No gas route.
Permitted plant: No (Zoning ban from Nov 9, 2026)Rentals under 12 months, no air permit: No
Pittsfield's new data center zoning section (Sec. 40-11.51) says: "On site operation of stationary engines, hydrocarbon generators, or other non-renewable energy sources for continuous, prime, peaking, or routine non-emergency energy supply is prohibited." It applies to all data centers and data processing centers (large, small and accessory) and to other 'High Resource Demand Facilities'. Generator testing is limited to weekdays 8 a.m. to 6 p.m. and 100 hours a year, and new generators must meet Tier 4 Final. A gas plant or rented gensets run as bridge power while a site waits for grid service would be continuous or prime supply, which the text bars. Data centers are a conditional use in the Industrial district only. The township board adopted the ordinance 7-0 on Oct 28, 2026; it takes effect Nov 9, 2026. The text does not say how it treats data centers built before then.
Permitted gas generation
The text bars on-site engines and generators for 'continuous, prime, peaking, or routine non-emergency energy supply', so a gas plant cannot serve as primary or bridge power. Emergency use is allowed but not defined.
Rentals kept under 12 months
The ban covers 'hydrocarbon generators' as well as stationary engines, without regard to ownership or how long they stay, so we read it as covering rented gensets (our reading; the text does not name rentals). Michigan's air rules on rentals are unclear (pass 1). Source
What's next
- Nov 9, 2026. ZOA #26-236 takes effect (township page). Flip status to in_force. Get the signed, published ordinance and compare it with the Oct 28 second-reading text.
Details
- Who it covers
- High Resource Demand Facilities and all data centers and data processing centers (large, small and accessory) in the township; treatment of facilities existing before Nov 9, 2026 not stated
- Where
- Pittsfield Charter Township only (Washtenaw County)
- Status
- Adopted, not yet in force
- Effective
- November 9, 2026
- Authority
- Pittsfield Charter Township, MI (Board of Trustees, ZOA #26-236, adopted at second reading Oct 28, 2026)
- Last checked
- November 8, 2026
Sources
- Pittsfield ZOA #26-236, Sec. 40-11.51, second-reading text (Board of Trustees packet, Oct 28, 2026, item 10.2) primary
On site operation of stationary engines, hydrocarbon generators, or other non-renewable energy sources for continuous, prime, peaking, or routine non-emergency energy supply is prohibited. (Sec. 40-11.51, Air Quality and Emissions 2.a.1, packet p.315)
- Pittsfield Charter Township, Data Center Ordinance page primary
The Board of Trustees voted 7-0 to adopt at Second Reading ZOA #26-236 ... will take effect on Monday, November 9, 2026.