New Jersey

Any non-emergency engine kept over 30 days needs a state permit; 25-ton NOx line statewide.

Only with a months-long air permit.

Permitted plant: Capped (Permit; 25-ton line)Rentals under 12 months, no air permit: No

In New Jersey, a reciprocating engine that stays more than 30 days at one site is a stationary engine, and any stationary engine of 37 kW or more that generates electricity, other than an emergency generator, needs a preconstruction permit and operating certificate before it is installed. So a rented gas or diesel fleet run as bridge power needs the same permit as a permanent plant. A site that could emit 25 tons a year of NOx or VOC faces LAER and emission offsets, and every county in the state is in an ozone nonattainment area. That is about 10 MW of modern gas engines running 24/7 (our estimate). NJDEP fined DataOne in Vineland $1,072,000 on Sep 22, 2026 for running 62 unpermitted 1,982 kW gas engines as stationary engines.

Permitted gas generation

Non-emergency engines of 37 kW or more need a preconstruction permit. At 25 tpy of NOx or VOC potential, the site needs LAER and emission offsets: about 10 MW of gas engines running 24/7 (our estimate, 6-18 MW).

Rentals kept under 12 months

Any engine kept more than 30 days at one site counts as stationary and needs the same permit. The 'construction engine' exclusion (a mobile generator used until power lines arrive, 12 months or less) is untested for a running data center; we read it as construction power only. Source

Details

Who it covers
new and existing sites; any engine of 37 kW or more kept over 30 days
Where
Statewide
Status
In force
Authority
NJDEP, N.J.A.C. 7:27-8 (permits and certificates) and 7:27-18 (Emission Offset Rule)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.