Oregon
Air permits for new or expanded data centers paused to July 1, 2027.
No gas route.
Permitted plant: No (Through Jul 1, 2027)Rentals under 12 months, no air permit: No
At the Governor's request (Oct 9, 2026 letter), Oregon DEQ has paused air and water permits for new or expanded data centers until July 1, 2027. DEQ told reporters it will end the pause sooner if the Governor says so, and that it is still working on applications up to a draft permit, then holding them. So no permit for a new or expanded data center can be finalized before then.
Permitted gas generation
Running gas 24/7 at a data center would almost certainly push it past its permitted emission limit, and going past that limit needs a modified DEQ permit. At the Governor's request DEQ has paused permits for new or expanded data centers.
Rentals kept under 12 months
Oregon requires a DEQ air permit for combustion power generation from any unit of 500 kW or more that isn't used only for emergencies, with no exemption for portable or nonroad units. A fleet of smaller units can still need a permit once the site's emissions pass its permit limit or 10 tons a year. For a new or expanded data center, that permit falls under the pause. A small temporary unit inside the site's existing emission limit may avoid a new permit, but DEQ hasn't said whether bridge power qualifies. Source
What's next
- Dec 31, 2026. Governor's data center advisory committee recommendations expected by the end of the year
- Jan 19, 2027. Oregon Legislature's 2027 regular session begins
- Jul 1, 2027. Pause ends unless lifted earlier or extended
Details
- Who it covers
- new and expanded data centers (existing sites not expanding are not clearly covered)
- Where
- Statewide
- Status
- In force
- Effective
- October 9, 2026
- Ends
- July 1, 2027
- Authority
- Governor of Oregon (Tina Kotek), letter to DEQ Director Leah Feldon; implemented by Oregon DEQ
- Last checked
- November 8, 2026
Sources
- Gov. Kotek letter to DEQ Director Leah Feldon, Oct 9, 2026 (copy hosted by OPB) primary
I am asking you to exercise your existing administrative authority and discretion to pause processing and issuance of air or water discharge permit applications until July 1, 2027 that involve new or expanded data center facilities within Oregon.
- Oregon DEQ, Data Center Air Quality Permitting, presentation to Governor's Data Center Advisory Committee, Jul 31, 2026 primary
"Non-emergency" operation such as maintenance, readiness testing, and dispatch operations are limited to 100 hours/year. Most permits have more restrictive operational limits.
- OPB, Oct 29, 2026 (DEQ spokesperson on implementation) secondary
DEQ will pause work until we receive further instructions from the Governor, or until July 1, 2027, whichever comes first
- DatacenterDynamics, Oct 2026 (DEQ statement) secondary
we have put a pause on the issuance of new or renewed air and water quality permits for data center facilities
- Oregon Capital Chronicle, Sep 16, 2026 (advisory committee timeline) secondary
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.