Dallas Township, PA

Zoning limits on-site generation to utility outages, 30 days in any 90.

No gas route.

Permitted plant: No (Zoning limit)Rentals under 12 months, no air permit: No

Dallas Township's zoning, amended Jul 28, 2026, says a data center's primary power will come from a public utility. On-site generation may run only when that primary source is unavailable, and no on-site generation may continue longer than 30 days in total in any 90-day period. Data centers are allowed only as a conditional use in the I-1 General Industrial District.

Permitted gas generation

Primary power must come from a public utility. On-site generation runs only when that source is unavailable, and no more than 30 days in any 90.

Rentals kept under 12 months

The 30-in-90-day limit applies to any on-site power generation, so rentals are covered (our reading). Source

Details

Who it covers
data centers, accessory structures, power substations and campuses approved under the township zoning ordinance
Where
Dallas Township only
Status
In force
Effective
July 28, 2026
Authority
Dallas Township Board of Supervisors, Luzerne County, PA (adopted Jul 28, 2026)
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.