Philadelphia area, PA

A 25-ton NOx/VOC line in the five Philadelphia counties, about 10 MW of gas engines.

Gas plant capped near 10–20 MW.

Permitted plant: Capped (Capped near 10 MW)Rentals under 12 months, no air permit: Unknown

In Bucks, Chester, Delaware, Montgomery and Philadelphia counties, Pennsylvania's nonattainment review applies once aggregated NOx or VOC increases exceed 25 tons a year, with offsets and the strictest controls. For gas that's about 10 MW of modern engines running 24/7 (our estimate). The area is Serious for the 2015 ozone standard, where the federal line would be 50 tons, but Pennsylvania's rule names these five counties at 25.

Permitted gas generation

Once aggregated NOx or VOC increases exceed 25 tons a year, nonattainment review applies: offsets at 1.2:1 and LAER (or BACT if offset internally). About 10 MW of gas engines running 24/7 (our estimate, 6-18 MW). Applying the 25-ton line to a brand-new facility is our reading of 127.203(b)(1).

Rentals kept under 12 months

Diesel nonroad rentals can use DEP's GP-11 general permit (compression-ignition only). Gas rentals have no general permit; they need a plan approval unless all exempt engines at the site stay under 6.6 tons of NOx a year (DEP exemption category 6). Our reading. Source

Details

Who it covers
new and existing facilities (increases aggregated over 5 or 10 years)
Where
Bucks, Chester, Delaware, Montgomery, Philadelphia counties
Status
In force
Authority
PA DEP (25 Pa. Code 127.203(b)); Philadelphia Air Management Services administers permits in Philadelphia; US EPA (classification)
Last checked
November 8, 2026

Sources