Nashville
Zoning bans on-site fossil power except emergencies and testing.
No gas route.
Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No
In Nashville and Davidson County, a data center may not run on-site diesel or gas generation as a primary, parallel or routine power source. Generators may run only for testing, commissioning, and defined emergencies (an NES outage, an NES request during grid strain, or a TVA EEA level 2 or 3 alert). Units must meet EPA Tier 4.
Permitted gas generation
On-site generation by any means except solar, wind, geothermal and waste heat is banned as a primary, parallel or routine power source. Data centers operating before July 31, 2026 may argue they're protected as an existing use; no court has decided this. Under the new zoning, adding square footage or capacity needs a new permit. A developer's federal lawsuit against the rules was dismissed on Oct 6, 2026, mostly without prejudice, so parts of it could be refiled.
Rentals kept under 12 months
The zoning ban covers on-site generation 'by any means' as primary power. We read that as covering rented units too; the ordinance doesn't name them. Source
What's next
- Dec 1, 2026. Companion moratorium on new data center permits ends; the gas ban stays.
Details
- Who it covers
- every data center tier (accessory, small, medium, large) permitted under the new zoning uses on or after July 31, 2026; small, medium and large data centers that add square footage or 'maximum utilization capacity' need a new permit. How it applies to data centers that predate the ordinance is unsettled.
- Where
- Nashville and Davidson County
- Status
- In force
- Effective
- July 31, 2026
- Authority
- Metropolitan Council of Nashville and Davidson County, Ordinance BL2026-1391 (Title 17 zoning code), as amended on third reading
- Last checked
- November 8, 2026
Sources
- BL2026-1391 legislation detail and history (Legistar) primary
passed on third reading as amended
- Amendment H to BL2026-1391 (Capp), adopted July 21, 2026 primary
On-site power generation by any means—except for solar, wind, geothermal, and waste heat recovery—as a primary, parallel, or routine source of electrical power for data center operations shall be strictly prohibited.
- Legistar action detail, July 21, 2026 (Amendment H adopted; final vote 36-0) primary
Council Member Capp offered Proposed Amendment 12, hereinafter referred to as Amendment H, and moved that it be adopted, which motion was seconded and approved by a voice vote of the Council.
- DCB Nashville, LLC v. Metropolitan Government, complaint (M.D. Tenn., filed Aug 11, 2026) secondary
approved by the Mayor on July 24, 2026, and became effective July 31, 2026
- WPLN: Nashville's data center ordinance lost a key environmental safeguard (July 20, 2026, before the final vote) secondary
an unlimited amount of on-site generation from fossil fuels during 'emergencies'
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.