Nashville

Zoning bans on-site fossil power except emergencies and testing.

No gas route.

Permitted plant: No (Zoning ban)Rentals under 12 months, no air permit: No

In Nashville and Davidson County, a data center may not run on-site diesel or gas generation as a primary, parallel or routine power source. Generators may run only for testing, commissioning, and defined emergencies (an NES outage, an NES request during grid strain, or a TVA EEA level 2 or 3 alert). Units must meet EPA Tier 4.

Permitted gas generation

On-site generation by any means except solar, wind, geothermal and waste heat is banned as a primary, parallel or routine power source. Data centers operating before July 31, 2026 may argue they're protected as an existing use; no court has decided this. Under the new zoning, adding square footage or capacity needs a new permit. A developer's federal lawsuit against the rules was dismissed on Oct 6, 2026, mostly without prejudice, so parts of it could be refiled.

Rentals kept under 12 months

The zoning ban covers on-site generation 'by any means' as primary power. We read that as covering rented units too; the ordinance doesn't name them. Source

What's next

Details

Who it covers
every data center tier (accessory, small, medium, large) permitted under the new zoning uses on or after July 31, 2026; small, medium and large data centers that add square footage or 'maximum utilization capacity' need a new permit. How it applies to data centers that predate the ordinance is unsettled.
Where
Nashville and Davidson County
Status
In force
Effective
July 31, 2026
Authority
Metropolitan Council of Nashville and Davidson County, Ordinance BL2026-1391 (Title 17 zoning code), as amended on third reading
Last checked
November 8, 2026

Sources

Check another site Need power here? Talk to us

For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.