Goochland County, VA (Technology Overlay District)
In the technology overlay, generators near homes may run only for testing and emergencies, defined as outages beyond the operator's control.
Likely no gas route.
Permitted plant: Likely no (Emergency-only rule)Rentals under 12 months, no air permit: Likely no
Goochland County's technology overlay district (TOD) standards say: "Generators cannot be operated other than for testing and during emergencies." They define emergencies as times when, "due to circumstances beyond the facility operator's control, the principal energy source to the facility is temporarily unavailable", when the utility directs generator use to protect the grid, or at the direction of emergency services. The limit sits in the noise standards, which apply "for conceptual master plans adjacent to either residentially-zoned property or mixed-use development with residential uses". The TOD standards reach data centers that are permitted only through the TOD, that take technology-zone incentives, or that are by right but adjacent to homes (Sec. 15-448.B). Data centers are by right in M-1 elsewhere with no generator-use limit. So the bar covers only part of the county. Whether a wait for first grid service counts as the principal energy source being "temporarily unavailable" is not settled by the text; we read a planned bridge as not an emergency (our reading).
Permitted gas generation
Where the TOD noise standards apply, generators may run only for testing and defined emergencies (outages beyond the operator's control, utility direction, emergency services). The definition could be argued to cover a grid-connection delay, so the bar on a bridge is our reading.
Rentals kept under 12 months
The limit covers all generators at a covered site, so we read it as covering rentals there (our reading). Outside covered sites, no zoning limit was found. Source
Details
- Who it covers
- TOD data center plans adjacent to residential zoning or mixed-use with homes (Sec. 15-448.B, 15-449.A(1)); not by-right M-1 sites away from homes
- Where
- Goochland County: Technology Overlay District sites, and by-right data centers adjacent to residential, only
- Status
- In force
- Effective
- November 6, 2025
- Authority
- Goochland County, VA (Board of Supervisors, Ord. No. 6471, Nov 6, 2025)
- Last checked
- November 8, 2026
Sources
- Goochland County Code Sec. 15-449.A(1)d(i), TOD design standards primary
Generators cannot be operated other than for testing and during emergencies. Emergencies means, for these purposes, when, due to circumstances beyond the facility operator's control, the principal energy source to the facility is temporarily unavailable
- Goochland County Code Sec. 15-448.B(3) primary
If the data center use is permitted by-right in the underlying zoning for the property and the property is adjacent to residentially-zoned property or a mixed-use development with residential use, then TOD standards in section 15-449, subsection A, apply.
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.