Southwest Washington (Clark, Cowlitz, Lewis, Skamania and Wahkiakum counties)
Rented engines kept under 12 months still need a local nonroad engine permit before they're installed.
Only with a months-long air permit.
Permitted plant: Possible (Permit needed, not paused)Rentals under 12 months, no air permit: No
Washington's state rule lets nonroad engines kept 12 months or less skip new source review, but the Southwest Clean Air Agency has its own rule. It says its nonroad engine permit requirements "apply to all nonroad engines" in its five counties, except listed exemptions such as installations under 500 horsepower in total that aren't tied to a stationary source, and engines that "replace utility power or utility powered equipment on a temporary basis (< 30 days in duration)". A permit "shall be issued by the Agency prior to the installation" of a covered engine. The application must show the engines meet the ambient air quality standards, a SEPA checklist is required, and the agency decides within 60 days of a complete application or starts public notice. A rented gas fleet sized for a 5–50 MW bridge is far above 500 hp, so it needs this permit (our reading). The permit path is open; this is a hurdle, not a ban.
Permitted gas generation
A permanent gas plant goes through SWCAA's stationary source review (SWCAA 400-110), which wasn't read for this row. No pause on data center air permits is in force in Washington as of Nov 8, 2026.
Rentals kept under 12 months
Nonroad rentals need a SWCAA nonroad engine permit before installation, with an air quality standards demonstration, a SEPA checklist, a 60-day decision clock and annual registration. Short utility-replacement use under 30 days with Tier-certified engines on ultra-low-sulfur fuel is exempt (400-045(3)(j)), which doesn't cover a months-long bridge. Source
Details
- Who it covers
- any site in Clark, Cowlitz, Lewis, Skamania or Wahkiakum County; engines operating in SWCAA jurisdiction before Nov 9, 2003 are exempt
- Where
- Clark, Cowlitz, Lewis, Skamania and Wahkiakum counties, WA
- Status
- In force
- Effective
- March 10, 2025
- Authority
- Southwest Clean Air Agency, WA (SWCAA 400 General Regulations for Air Pollution Sources, effective March 10, 2025)
- Last checked
- November 8, 2026
Sources
- SWCAA 400-045, Permit Application for Nonroad Engines primary
The requirements of this section apply to all nonroad engines as defined in SWCAA 400-030 except for those identified in section (3) below.
- SWCAA 400-046(2)(a), Application Review Process for Nonroad Engines primary
a nonroad engine permit shall be issued by the Agency prior to the installation, replacement or alteration of any nonroad engine subject to the requirements of SWCAA 400-045 and this section.
- SWCAA 400-020(1), Applicability primary
The provisions of this regulation shall apply within Clark, Cowlitz, Lewis, Skamania and Wahkiakum Counties of Washington State.
For information only, not legal advice. Confirm with your air agency and fire marshal before you rely on it. Spot an error? Email tyler@relayenergy.us.