Serious ozone area: new generation over 50 tons a year of NOx or VOC needs major-source review.

Gas plant capped near 10–20 MW.

Permitted plant: Capped (Capped near 20 MW)Rentals under 12 months, no air permit: Unknown

In Milwaukee and Ozaukee counties and the eastern parts of Racine, Washington and Waukesha counties, new generation that could emit 50 tons or more of NOx or VOC a year triggers major-source review. For gas that is roughly 20 MW of modern engines running 24/7 (our estimate). Port Washington (Ozaukee) and, by our reading of the boundary, Mount Pleasant (eastern Racine) are inside. Not a ban.

Permitted gas generation

Above 50 tpy, nonattainment NSR. Below it, a DNR construction permit unless an NR 406.04 exemption applies.

Rentals kept under 12 months

Our reading: Wis. Stat. 285.01(41) counts a source 'capable of being transported to a different location' as a stationary source, so a construction permit is needed unless NR 406.04 exempts it; but NR 400.02(143) calls construction-site generators 'semistationary sources'. DNR practice not confirmed. Source

What's next

Details

Who it covers
new and existing
Where
Racine Co.: inclusive and east of Hwy 45 / Washington Ave / S. Beaumont Ave; Washington Co.: inclusive and east of County H / N Main St-Old US 45 / WI-60 Trunk E / WI-164 S; Waukesha Co.: inclusive and north of I-94 and inclusive and east of Hwy 67
Status
In force
Effective
January 16, 2025
Authority
US EPA (40 CFR 81.350); Wisconsin DNR (nonattainment NSR, ch. NR 408, not read)
Last checked
November 8, 2026